Purpose: a day at 8:30 start points IBControllerStart. Bat, check the Trader Workstation (TWS) 963 if the instance is running, if you're running, are no longer repeated start instance; Otherwise, start a new instance;

Phenomenon is described and the detailed steps:
1 I according to the following link to describe the steps in local deployment TWS and IBController folder, through manual under the double-click IBController IBControllerStart. Bat, TWS normally open and normal work,
https://github.com/memoryfraction/ib-controller/blob/master/userguide.md

2 I hope step 1 can be done automatically, and hope that by planning tasks, Windows 2008/under the Windows 7 have been trying to plan tasks, were unable to automatically Start IBControllerStart. The bat, import plan task is through the Start of step 1 links TWS Live (daily). XML import, have local user name and password for the configuration, screenshots are as follows:

In the figure above, point the "Run", have no reaction, path has been verified,


3 by planning task start other batch bat file that can be work; For example I built a simple on disk C bat file
 rundll32 user32. DLL, LockWorkStation 

By planning tasks, the trigger condition is met can trigger and logout user,

Seek solutions


CodePudding user response:

Double-click alone no problem, the task plan is no problem? That I don't know is what circumstance,,,